Two quotes for a bathroom of the same size can show very different amounts. Very often, the difference comes down to labour time: in a renovation, it is not only the price of the materials that counts, it is above all the time needed to install them. But site access, the existing condition and the level of finish also play a part. Here are a few examples among the situations we come across most often. The list is not complete: every project has its own particularities, and it is the site visit that brings them to light.
1. The tile format
Laying 60 × 60 cm porcelain stoneware and laying small irregular zellige tiles is not the same job. Per square metre, the large format is laid in fewer than three tiles. Zellige takes dozens, each laid by hand, with many more joints, more cuts and irregularities to make up.
For the same area, laying time can therefore be much longer. This is also why changing the tiles after the quote has been signed (for example switching from a large format to a smaller one) changes the price. We prefer to discuss it beforehand, to avoid unpleasant surprises.
2. The number of paint colours
A single colour throughout the house makes for a smooth project. Several colours take more time:
- each colour has its own drying times, and the rooms no longer follow on as easily;
- the protection (dust sheets, masking tape) has to be put back at each change of colour;
- paint is bought as precisely as possible for each colour, and the leftovers in each tin are lost.
Choosing several colours is not a whim: it often gives an interior a lot of character. It is simply useful to know that it is reflected in the quote.
3. Small, very technical rooms
People often think that a small bathroom must cost much less than a large one. In reality, a 4 m² bathroom with a toilet, shower, vanity unit, mirror, towel radiator, extractor fan, waterproofing and tiling costs barely less than the same room at 8 m².
Why? Because the number of tasks is the same: the same connections, the same fittings to install, the same waterproofing steps. Only the quantities of tiles and paint change. And in a small space, work is rarely any faster.
4. Site access
A flat on the 4th floor without a lift, a narrow staircase, a street where parking is difficult: all of this takes time. Materials are carried up by hand, rubble is carried down the same way, and every trip counts. In Brussels, parking is often paid, and a skip on the road requires authorisation from the municipality. In a building, the co-ownership rules may also impose working hours or forbid using the lift for materials.
5. An occupied home or common areas to protect
Standard protection is included in the site set-up. But if you live in the home during the work, more protection is needed, tidying and cleaning every day, and sometimes working room by room. The same applies when a whole stairwell has to be protected up to the 4th floor. In these cases, an additional protection package is included. Living at home during the work
6. The existing condition
Walls that are not plumb, a floor to be levelled, plaster coming away, damp, old lead pipes, an electrical installation to be brought into compliance: the more damaged the existing structure, the more preparation is needed before laying the slightest finish. Some of these points only show once the walls or floors are opened up. Where extras during a project come from
7. Demolition and waste removal
Removing tiles laid on top of old tiles, breaking up a thick screed or dismantling a complete kitchen means a lot of work and volume to remove, with a skip or several trips to the recycling centre. In old buildings, some materials (old adhesives, floor tiles, fibre cement sheets) may contain asbestos: they must then be tested and, if necessary, removed following a specific procedure.
8. Moving water, waste pipes or electrics
Keeping the toilet, shower and sink where they are costs considerably less than moving them. Moving a kitchen to another wall or putting the shower on the other side of the room means running new water supplies, creating waste pipes with a sufficient fall, and sometimes opening up or raising the floor. Walk-in shower: waterproofing, fall and drainage
9. The level of finish and the laying pattern
Herringbone parquet or diagonally laid tiles require more cuts and generate more waste than straight laying. Tile corners mitred at 45° instead of a trim, niches in the shower, a perfectly smooth ceiling even in raking light, made-to-measure furniture: every carefully finished detail translates into hours of work.
10. Structural work
Opening a load-bearing wall or altering a roof structure requires an engineer’s study, a beam, temporary propping and sometimes a planning permit. These are essential steps, which weigh on the budget and the schedule. Opening a load-bearing wall: permit and engineer
These examples are only part of what can make a quote vary. That is why we always visit the site before pricing, and why every quote is drawn up for your home and your project.
Our advice
Make your finishing choices before signing the quote, and feel free to ask us about the impact of an option on the price. We can often suggest an alternative that keeps the spirit of your project while keeping the budget under control.