Opening the kitchen onto the living room, joining two rooms: it is one of the jobs that transforms a home the most. When the wall to be opened is load-bearing, the project is entirely feasible, but it needs preparing.

Load-bearing or not?

A load-bearing wall carries the weight of floors, other walls or the roof. Its thickness, its position in the building and the direction of the joists give clues, but only a professional can confirm it. We check this during the visit.

A structural engineer

To open a load-bearing wall, what it supported must be replaced by a beam, usually in steel. A structural engineer calculates the loads and sizes the beam and its supports. This is essential for the building’s safety. You can appoint the engineer yourself, or we can take care of it.

A permit and an architect

Altering the structure of a building is generally not considered “minor” work. In Brussels as in Wallonia, opening a load-bearing wall generally requires a planning permit, and therefore an architect. The exact rules depend on the Region and the municipality: your municipality’s planning department remains the reference. In Brussels, Homegrade also gives free advice.

In a building with joint ownership, the approval of the general meeting is in principle required, since a load-bearing wall is part of the building’s structure.

How the work is carried out

  1. Propping: props temporarily support the floors.
  2. The opening: the wall is cut according to the engineer’s plans.
  3. Installing the beam and its supports.
  4. Finishing: boxing in the beam, plastering, floor joins, painting.

It is a dusty, noisy job. It is often simpler to plan it before the other finishing work.

What if the wall is not load-bearing?

A non-load-bearing partition can generally be removed without a permit or an engineer, unless special rules apply (listed building, joint ownership). Watch out, though, for cables and pipes that may run through it.