A renovation project is a chain of steps that depend on one another. When one falls behind, the next ones wait. Here are the most common causes, and what can be done to avoid them.

1. Delivery times

Windows, made-to-measure doors, some tiles, bathroom furniture: several weeks can pass between order and delivery. For windows, it is often more than a month.

The solution: choose and order early, as soon as the quote is signed.

2. Drying times

A screed, a filler or a paint needs time to dry before the next step. A traditional screed can need several weeks before it can take a parquet floor. That time cannot be made up: laying too early risks cracks or lifting.

The solution: allow for it in the schedule, and organise other work during drying.

3. Late choices or changes of mind

Tiles not yet chosen, a change of mind about where a socket or shower goes: every hesitation can hold up a team.

The solution: make the main choices before the project starts.

4. Discoveries when opening up

In an old building, there are sometimes surprises: lead pipes, a damaged beam, a wall in poor condition, damp. The work then has to be adapted.

The solution: a quote that clearly flags the items “to be confirmed on opening”, and a quick decision when a surprise appears.

5. Permissions

A planning permit, the approval of the co-owners or a road occupancy permit take time. These steps must be completed before the work concerned starts.

6. Holiday periods

The construction industry’s summer holidays and the Christmas period slow down suppliers and teams. It is best to take this into account if you have a deadline.

And to get started?

The time before a project can start varies: sometimes the following week, sometimes the following month. It depends on our schedule, the size of the project, the materials to order and their delivery times, and any preliminary steps (permit application, engineer’s calculations…).

Our approach

If a date matters to you (moving in, letting, a birth), tell us from the start. We talk it through together and organise the project accordingly.

Tell us about your project